SIZE OF WWTP 10 000 m3/day (2 641 000 GPD)
END USER Water and wastewater utility provider, OAO Vodokanal
CUSTOMER OOO SibKapStroy
START OF OPERATION August, 2017
Issue
In Gorno-Altaysk WWTP, instead of mechanical sludge dewatering, sludge was dewatered in outdated sludge drying beds. Malodor from sludge drying beds disturbed residents from nearby leaving area, therefore regional authorities made a decision to fund the construction of a new sludge dewatering facility.
Solution
Based on national requirements, 3 units (2 duty and 1 stand-by) of MDQ-352 C were installed.
Results
Type of sludge | Mixture of primary sludge and waste activated sludge |
Unit Sludge Supply | 3-3.5 m3/h (13-15 GPM) 150-160 kg DS/h (330-350 lb DS/h) |
Feed Sludge DS Concentration | 4-6 % |
Cake DS Concentration | 23-27 % |
Opetarion time | 10 h/d |
Average Polymer Dose | 3.5-4.5 g/kg DS (7-9 lb/ton DS) |
Unit Daily Power Consumption | 18 kW*h |